Client
Považská vodárenská spoločnosť, a.s.
Superior Contractor
Consortium Papradňanská dolina, TUCON – LSS – VODEKO
Construction period
August 2011 – July 2013
Objects description:
- SO 01 Main Sewer
- SO 06 Jasenica Sewage Collector
- SO 07 Stupné Sewage Collector
- SO 08.1 Stupné Pumping Station
- SO 08.2 Stupné Pumping Station
- SO 08.3 Stupné Pumping Station
- SO 08.4 Papradno Pumping Station
- SO 09 Brvnište Sewage Collector
- SO 10 Papradno Sewage Collector
- PS 05.1 Stupné Pumping Station
- PS 05.2 Stupné Pumping Station
- PS 05.3 Stupné Pumping Station
- PS 05.4 Stupné Pumping Station
Construction technology:
It is a gravity sewer in the sewer network in the length of 32.4 km, including sewer taps in the number of 1 882 units and four pumping stations. The works are containing of trench excavation in the width up to 2m, shafts excavation, placing and installation of pipelines including their rear backfilling, construction of sewerage shafts and a subsequent adjustment of road´s covers.