Client
Považská cementáreň, a.s. Ladce
Construction period
November 2009 – January 2010
Objects description:
- mine gallery, used for vertical and later horizontal transport of limestone excavated in Butkov mining area, designed for limestone excavation by Považská cementáreň, a.s. Ladce
- the length of horizontal mine gallery is 590.0 TM and it can be found at elevation 385.00 m a.s.l.
Construction technology:
Liquidation of a mining work by removal winch VTA 4000, transport winch VTA 1000 and rail vehicles.
Realized works:
- removing of machinery equipment from under dump of vertical part, inclosure of the horizontal part of mining work on the bottom of the dump chamber
- removing of the TP 630/1000 belt conveyor, separate ventilation, pipe lines, power lines, a rail track, machinery equipment and steel structures from the gallery, final reinforcement of the project – steel TH reinforcement and concrete casing, a shelter located at the entrance to the gallery and final inclosure of the gallery